Supplier Compliance

Purchase Order Quality Requirements

 

*QUALITY SYSTEM REQUIRED

If required by MK Manufacturing customer, the supplier shall establish and maintain an effective Quality System in compliance with the requirements of ISO 9001, AS9100, NADCAP, etc. The supplier's Quality System is subject to On-Site or Off-Site audit, verification, approval and/or disapproval by MK Manufacturing repersenitive

 

*APPROVAL & CHANGES

Supplier is not authorized to approve changes in product or process on this purchase order.

 

*MRB AUTHORITY

Material review board authority is not authorized on this purchase order.

 

*RAW MATERIALS

Raw materials used on this purchase order shall be accompanied with original mill certifications, chemical and/or physical test results. The supplier shall certify the specific requirements defined on the purchase order. Only if requested by customer.

 

*LOT CONTROL/TRACEABILITY

Where, and to the extent that, traceability is a specific requirement, the supplier shall apply a unique identification to the individual product, material or batch (i.e.: Lot #, Date code) per PO requirements. This identification data shall be recorded and traceable to related suppliers records.

 

*SUPPLIER QUALITY RECORDS

The supplier shall maintain suitable records (inspection reports, test reports, material certifications, PO requirements, etc) to serve as evidence of conformance with specified requirements. Such records shall be legible and traceable to the product involved. These records shall be maintained for a minimum of seven (7) years from the date of the final manufacture or as stated otherwise in the PO.

 

*SUBMISSION OF NONCONFORMING PRODUCT

Nonconforming product returned to supplier by MK Manufacturing, and subsequently resubmitted to MK Manufacturing shall bear adequate identification of such nonconformance. Identification may be on the previously non-conforming articles, materials, or applicable supplier's records. The supplier shall provide evidence that the root cause of the nonconformance was corrected and that actions were taken to prevent recurrence.

 

*SUPPLIER NOTIFICATION OF NONCONFORMING PRODUCT DELIVERED

When the supplier has determined that nonconforming product(s) have been delivered to MK Manufacturing, the supplier shall notify the buyer within twenty-four (24) hours of the initial discovery. The supplier shall use receipt acknowledgement e-mail or other positive notification method. The notification shall include the supplier name, MK Manufacturing PO number, part number and description, affected quantity and serial numbers (if applicable), packing slip numbers and a brief description of the nonconforming condition.

 

*ACCESS TO SUPPLIER'S FACILITIES

During contract performance, the supplier shall grant reasonable access to the supplier's facilities to the representatives of MK Manufacturing, MK Manufacturing customers, US government and/or regulatory agencies for the purpose of evaluating supplier's conformance to all PO/Contract requirements. When applicable, the access requirement shall be flowed-down by the supplier to the supplier's sub-tier sources.

 

*FIRST ARTICLE INSPECTION REPORT

Supplier shall perform a First Article Inspection on all new product, drawing revision changes, or process changes. Supplier shall forward one (1) copy of the First Article Inspection Report to the buyer. If only requested by customer.

 

*CERTIFICATE OF CONFORMANCE

Included with each shipment to MK Manufacturing shall be a Certificate of Conformance signed by the supplier's Quality Representative indicating as a minimum of the process description, process number, name and address of the supplier, the purchase order and part number/revision.

 

*MATERIAL TRACEABILITY

Material used on this Purchase Order must be positively identified to maintain traceability to original manufacturer's Heat, Lot or Batch number according to original mill certifications and/or test results. Traceability must be maintained throughout the manufacturing process and completed product.

 

*CONTROL OF SUB-TIER SOURCES

The supplier is responsible for meeting all PO/Contract specified technical and quality requirements, whether the supplier performs the work or it is performed by the supplier's sub-tier sources. When the supplier uses sub-tier sources to perform work on products and/or services scheduled for delivery to MK Manufacturing, the supplier shall flow-down to sub-tier sources all of the applicable technical and quality requirements of the original MK Manufacturing PO/Contract.

 

*REQUIREMENTS FOR QUALIFICATION OF PERSONNEL

Where applicable, only qualified/certified personnel shall be used based on process specification requirements (NDT, etc). Records shall be maintained of the personnel qualifications/certifications.

 

*DELEGATED AUTHORITY OF INSPECTION FOR RAW MATERIAL

Where applicable, MK Manufacturing authorizes and requires the supplier to perform receiving inspection on all raw material purchased by MK Manufacturing  and delivered by another supplier. Original shipping and certification documents must be included with shipments made by supplier.